BUSI 680
Updated Case 6.2: Montview Stadium Case

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 1, 2020, and be completed in time for the start of the 2024 season. A penalty clause of $100,000 per day of delay beyond April 3 is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

Assignment

Given the information provided in Table 1, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the April 3rd deadline? How long will it take? How many working days are projected?

2. What is the critical path for the project? List the activities on the critical path.

3. Based on the schedule would you recommend that G&E pursue this contract? Why or why not?

Technical Details for the Shoreline Baseball Stadium

For the purposes of this case assume the following:

1. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

3. The crews work standard days, Monday through Friday.

Table 1: Montview Baseball Stadium Case

 

ID Activity Duration (days) Predecessor(s)
1 Clear stadium site 75
2 Demolish present stadium 40 1
3 Establish construction site 70 2
4 Drive support piling 110 3
5 Install lower bowl 125 4
6 Install main concourse 110 5
7 Install playing field 95 5
8 Construct upper steel bowl 110 5
9 Install seats 160 8
10 Build luxury boxes 90 8
11 Install Jumbotron 25 8
12 Install infrastructure 110 8
13 Build steel canopy 80 9
14 Install lighting 25 9
15 Construct roof supports 90 3
16 Build roof 150 15
17 Construct roof racks 90 13
18 Install roof supports 90 16,17
19 Final inspection 25 7,10,12,14,18

 

 

 

 

 

 

https://newconnect.mheducation.com/vf

Page 2 of 2

Essay writing help – BUSI 680 Mont-view Stadium Case Online Essay Writing Agency – Critical Assignment.

Write my Essay. Premium essay writing services is the ideal place for homework help or essay writing service. if you are looking for affordable, high quality & non-plagiarized papers, click on the button below to place your order. Provide us with the instructions and one of our writers will deliver a unique, no plagiarism, and professional paper.

Get help with your toughest assignments and get them solved by a Reliable Custom Papers Writing Company. Save time, money and get quality papers. Buying an excellent plagiarism-free paper is a piece of cake!

All our papers are written from scratch. We can cover any assignment/essay in your field of study.

PLACE YOUR ORDER